During a recent Modicon remote I/O service call at a large oil refineries tank farm which had been having intermittent communication, an unusual problem was discovered. The system had been having communication drop-outs intermittently for several weeks. During that time, several F connectors, taps, J890s and sections of trunk cable had been replaced attempting to fix the problem. Unfortunately, none of these parts repaired the problem. Delta had serviced this system several years ago and is familiar with the system layout. The system is a very large system with over 5000 feet of RG-11 cable. It is a splitter type system. Delta suggested utilizing a set of fiber optic modems to isolate the two legs of the split system to increase the signal levels and assist in any future troubleshooting. Delta was commissioned to design and build a panel containing the necessary components. It was completed and shipped to the client. They mounted the panel and notified Delta that they were ready for the unit to be installed and certified. Once on-site, the Delta engineers set out to first discover the issue that initially caused the failure. A TDR was placed on the system and immediately an anomaly was noticed on the first section of trunk cable. This cable was installed overhead on telephone poles utilizing messenger cable. There was no time to properly hang the replacement cable before production had to be resumed, so the cable was installed in a temporary fashion by attaching it to a chain-link fence that was nearby. New connectors were installed and the cable connected to the system. The fiber optic panel was connected as well. The system was then ready to be certified. The TDR test was completed, then the loss measurement and attenuator tests were to be completed. Both of these were being done in an alternating fashion to save time. As the testing progressed, it was noticed that some of the test data was out of specification. The remote drops were still having retries and drop-outs. The TDR was used to reinspect the cable structure and all was found to be correct, with the exception that there was a small amount of AC on the data stream. Since the routing of the temporary cable was different from the original cable, electrical noise was suspected. A ground was installed on the tap at one end of the new cable. The AC disappeared and the errors were gone as well. Testing was resumed and all was found to be within specification. The system was returned to full production with no errors. In the process of replacing the defective cable, and choosing to install a temporary cable in a different routing location, noise was inadvertently introduced into the system. Fortunately the Delta engineers are experienced in these systems and quickly located the introduced problem.
-
Recently on Delta’s blog…
Golden Oldies…
- March 2019
- September 2018
- June 2018
- May 2018
- April 2018
- September 2017
- August 2017
- July 2017
- March 2017
- February 2017
- January 2017
- November 2016
- September 2016
- July 2016
- February 2016
- January 2016
- November 2015
- August 2015
- July 2015
- June 2015
- February 2015
- January 2015
- December 2014
- November 2014
- October 2014
- September 2014
- August 2014
- July 2014
- June 2014
- May 2014
- April 2014
- March 2014
- February 2014
- January 2014
- October 2013
- May 2013
- April 2013
- March 2013
- February 2013
- December 2012
- November 2012
- October 2012
- September 2012
- August 2012
- July 2012
- June 2012
- May 2012
- April 2012
- March 2012
- February 2012
- January 2012
- December 2011
- November 2011
- October 2011
- September 2011
- August 2011
- July 2011
- June 2011
- May 2011
- April 2011
- March 2011
- February 2011
- January 2011
- November 2010
- October 2010
- September 2010
- June 2010
- May 2010
- April 2010
Subjects
2002 Volumes
2003 Volumes
2004 Volumes
2005 Volumes
2006 Volumes
2007 Volumes
2008 Volumes
2009 Volumes
2010 Volumes
Blogroll